A lot has happened since my last up-date. We have now completed all the City required changes necessary to our drawings and have received final approval of our project from the City. We now have permissionto pick up our permit anytime we desire. We have worked hard to determine final construction cost and have discovered that [...]
We have received the Cities review comments back for phase 1 parking lot and entrance driveway and have analysied them. The major items that needed to be address were identified and assigned for corrections as required. Modificaitons to our landscape plan are required and are underway at this time. The need to record on our deed and title [...]
Parking Lot Up-date 6-14-10
Garage/Parking lot sale
Spare Change Sunday
Preliminary parking lot plans ready for review
Contract signed for design services
The $22,750.00 design contract for design services was signed the last week of February 2010. It is anticipated that all design work should be completed and ready to turn in for City of Eugene review by the first of April. The intent is to do everything necessary to have the permits in hand for a [...]
Campus Projects Progress

The Elders invite all comments concerning the improvement projects lined out on this page. Phase 1 involves adding 57 parking spaces and upgrading the playground area. The approximate funds needed are $200,000. Faithful prayer and giving hearts will make this a reality and it is only the beginning of a wonderful and effective tool for Christ. Please [...]
2G Construction selected as design build contractor
After a process that included receipt of proposals from four contractors and a review from the parking lot capital project committee, negotiations were opened with 2G Construction. Their proposal was the most complete and representative of project as we envision it. Approximate total cost will be in the $250,000 range. To date $160,000 is in [...]